=== When Detector Head Arrives from LBL === | |||
1. | |||
=== CIN Modules === | === CIN Modules === |
Revision as of 22:46, 8 January 2013
TO DO
When Detector Head Arrives from LBL
1.
CIN Modules
- LBNL to fill in?
Top Module
- LBNL to fill in
Digitizer Module
- LBNL to fill in
Chiller
- Need to install into detector heads
GUI
- Add fCRIC mask to GUI
- Keep consolidating redundant routines
COMPLETED TASK
Vacuum Chambers
- APS has two vacuum chambers built
Chiller System
- APS has two Systems
GUI
- Put under CVS control
- Added image viewer
- Added Expousre controls
- Add fCRIC Timing waveforms
- Sync/Update Exposure control when other data is sent down
- One button to send file to FPGA and update GUI
- Currenly when you send down a configuration file it does not update the GUI's waveforms, and bias windows, unless you are in the the waveform or bias window.
ATCA Shelves
- Arrived from
- Linux installed
- Lots of software installed
- Raid array mounted and tested using 10Gbit Links
Clock Module
- 8-1-2012 Shipped 12 tested Clock Modules to LBL
Need to fully build 12 Clock Modules, LBNL will provide metal plates (3 per module) Order 2 blank PCB
- 4-2-2012 PCBs ordered (15 days)
- 4-3-2012 Assembly ordered
Power Supply
- 12-20-2012 Added connector on back for interlock system. When open power supply turns off.