Difference between revisions of "To Do List"

From Fast CCD Detector
Jump to navigationJump to search
Line 48: Line 48:
* Lots of software installed
* Lots of software installed
* Raid array mounted and tested using 10Gbit Links
* Raid array mounted and tested using 10Gbit Links
=== Clock Module ===
* 8-1-2012 Shipped 12 tested Clock Modules to LBL
Need to fully build 12 Clock Modules, LBNL will provide metal plates (3 per module)
Order 2 blank PCB
* 4-2-2012 PCBs ordered (15 days)
* 4-3-2012 Assembly ordered

Revision as of 22:44, 8 January 2013

TO DO

CIN Modules

  • LBNL to fill in?

Clock Module

  • 8-1-2012 Shipped 12 tested Clock Modules to LBL
  • Need to fully build 12 Clock Modules, LBNL will provide metal plates (3 per module)
  • Order 2 blank PCB
  • 4-2-2012 PCBs ordered (15 days)
  • 4-3-2012 Assembly ordered

Top Module

  • LBNL to fill in

Digitizer Module

  • LBNL to fill in

Chiller

  • Need to install into detector heads

Power Supply

GUI

  • Add fCRIC mask to GUI
  • Keep consolidating redundant routines

COMPLETED TASK

Vacuum Chambers

  • APS has two vacuum chambers built

Chiller System

  • APS has two Systems

GUI

  • Put under CVS control
  • Added image viewer
  • Added Expousre controls
  • Add fCRIC Timing waveforms
  • Sync/Update Exposure control when other data is sent down
  • One button to send file to FPGA and update GUI
  • Currenly when you send down a configuration file it does not update the GUI's waveforms, and bias windows, unless you are in the the waveform or bias window.

ATCA Shelves

  • Arrived from
  • Linux installed
  • Lots of software installed
  • Raid array mounted and tested using 10Gbit Links

Clock Module

  • 8-1-2012 Shipped 12 tested Clock Modules to LBL

Need to fully build 12 Clock Modules, LBNL will provide metal plates (3 per module) Order 2 blank PCB

  • 4-2-2012 PCBs ordered (15 days)
  • 4-3-2012 Assembly ordered