=== CIN Modules ===
=== CIN Modules ===
Build??
* LBNL to fill in?


=== Clock Module ===
=== Clock Module ===
Need to fully build 12
*Need to fully build 12 Clock Modules, LBNL will provide metal plates (3 per module)
Order 2 blank PCB
*Order 2 blank PCB


=== Top Module ===
=== Top Module ===
?
* LBNL to fill in


=== Digitizer Module ===
=== Digitizer Module ===
?
* LBNL to fill in


=== Chiller ===
=== Chiller ===
Line 20: Line 20:


=== ATCA Shelves ===
=== ATCA Shelves ===
APS still waiting for 2 from Shelves from ZNYX.
*APS still waiting for 2 from Shelves from ZNYX.


=== GUI ===
* Add fCRIC Timing waveforms
* Sync/Update Exposure control when other data is sent down
* One button to send file to FPGA and update GUI
* Add fCRIC mask to GUI
* Currenly when you send down a configuration file it does not update the GUI's waveforms, and bias windows, unless you are in the the waveform or bias window.
* Allow user to choose which waveforms to view (will need when fCRIC waveforms are added)
* Keep consolidating redundant routines


== DONE ==
== COMPLETED TASK ==


=== Vacuum Chambers ===
=== Vacuum Chambers ===
Line 31: Line 39:
*LBNL has finished chiller system design and is in the process of building the flex-cool custom probe heads.
*LBNL has finished chiller system design and is in the process of building the flex-cool custom probe heads.
*APS has started the process to order two systems.
*APS has started the process to order two systems.
=== GUI ===
* Put under CVS control
* Added image viewer
* Added Expousre controls

Revision as of 20:53, 2 March 2012

TO DO

CIN Modules

  • LBNL to fill in?

Clock Module

  • Need to fully build 12 Clock Modules, LBNL will provide metal plates (3 per module)
  • Order 2 blank PCB

Top Module

  • LBNL to fill in

Digitizer Module

  • LBNL to fill in

Chiller

  • LBNL needs to build custom flex-cool probe heads and send to FTS Systems

Power Supply

ATCA Shelves

  • APS still waiting for 2 from Shelves from ZNYX.

GUI

  • Add fCRIC Timing waveforms
  • Sync/Update Exposure control when other data is sent down
  • One button to send file to FPGA and update GUI
  • Add fCRIC mask to GUI
  • Currenly when you send down a configuration file it does not update the GUI's waveforms, and bias windows, unless you are in the the waveform or bias window.
  • Allow user to choose which waveforms to view (will need when fCRIC waveforms are added)
  • Keep consolidating redundant routines

COMPLETED TASK

Vacuum Chambers

  • APS has two vacuum chambers built

Chiller System

  • LBNL has finished chiller system design and is in the process of building the flex-cool custom probe heads.
  • APS has started the process to order two systems.

GUI

  • Put under CVS control
  • Added image viewer
  • Added Expousre controls