=== Chiller ===
=== Chiller ===
APS waiting for go ahead to order two
* LBNL needs to build custom flex-cool probe heads and send to FTS Systems


=== Power Supply ===
=== Power Supply ===

Revision as of 20:27, 2 March 2012

TO DO

CIN Modules

Build??

Clock Module

Need to fully build 12 Order 2 blank PCB

Top Module

?

Digitizer Module

?

Chiller

  • LBNL needs to build custom flex-cool probe heads and send to FTS Systems

Power Supply

ATCA Shelves

APS still waiting for 2 from Shelves from ZNYX.


DONE

Vacuum Chambers

  • APS has two vacuum chambers built

Chiller System

  • LBNL has finished chiller system design and is in the process of building the flex-cool custom probe heads.
  • APS has started the process to order two systems.